Toilet Construction

 

 

Construction of toilet is a very simple thing. Following are the steps.

 

 

Step 1 - Preparation

 

a. Form a village hygiene committee.

 

b. Identify the families interested in building a toilet.

 

c. Call Vasudev Deshpande at 97422-04624 or Srinivas Deshmukh at 94835-00810 on getting started.

 

d. Arrange an awareness program in the village

 

e. Get each family ready to invest at least Rs.10,000 towards construction of a toilet

 

Step 2 - Resource management

 

a. Open a joint account at the village.

 

b. Each family deposits the amount

 

c. Identify a local contractor

 

d. Give the contract

 

e. Get the work started

 

Step 3 - Construction work

 

a. Village committee does supervision of the work

 

b. Parishudh also provides a helping hand and an incentive of up to Rs.8,000 each toilets

 

c. Toilets are constructed and handed over

 

Toilet construction work is in progress at the following now.

 

SL.No Village Taluka Enrolled Excavation PCC Septic tank Toilet Room Delivered
1 Madyal Aland 66 50 50 45 40 35
2 Madanhipparga Aland 25 23 23 23 10
3 Yalsangi Aland 4 4 4 4 3 3
4 rudhrawadi Aland 31 25 25 18 8
5 Jambiga Aland 18 10 6    
6 Gunj Bablad Aland 21 15 18 5  
7 Suntnoor Aland 16 15 15 10  
8 Belambgi Aland 22 18 18 4  
9 Gotur Chattapur 16 11 11 11 11 11
10 Mugalnagon Chattapur 24 15 15 15 14
11 Ghanagapur Afzalpur 26 12 16 16 12 12
12 Honkiranagi Gulbarga 23 16 16 11 11
13 Rajnal Gulbarga 16 16 16 16  
14 Parthapad Gulbarga 12 8 6
15 Nandur(K) Gulbarga 30 30 30 30 30 30
16 Maradgi(SN) Jewargi 21 21 21 18
17 Gawar Jewargi 68 56 56 40 38 32
18 Kusnoor Gulbarga 15
19 Sharansarasgi Gulbarga 10 6 6 2
20 Kellour Jewargi 12 12 12 12
Total 476 363 364 280 177 123

 

 

 

 

 

 

 

 

 

 